PNC RAJASTHAN HIGHWAYS PRIVATE LIMITED (Group Company of PNC Infratech Limited)
Four / Two laning with paved shoulder from Km 0.000 to Km 83.453 of Dausa – Lalsot – Kauthun section of NH-11A extension in the State of Rajasthan under NHDP Phase IV on Hybrid Annuity Mode.

Salient Features of Project
Name of Authority | National Highways Authority of India |
Name of Concessionaire | M/s. PNC Rajasthan Highways Private Limited |
Name of the EPC Contractor | PNC Infratech Ltd. |
Design Consultant | Consulting Engineers Group |
Name of Independent Engineer | Sai Systra Group |
Project Road Length | 83.453 Kms. |
Concessionaire EPC | Rs. 745.00 Crores |
Concession Agreement Cost or Bid project Cost | Rs. 881.00 Crores |
Date of Concession Agreement | 7th November 2016 |
Financial Closure Date | 03rd April 2017 |
Appointed Date | 31st May 2017 |
Construction Period | 910 days |
Concession period | 15 Year From PCOD/COD excluding Construction period 910 Days |
PCOD | 14TH Feb 2020 |
Final COD | 05th Nov 2020 |
Total length | 83.453 kms |
Length of Four lane section | 34.225 Kms |
Length of Two lane section | 49.228 Kms |
No. of Toll Plaza | 2 (Two) |
Bypass | 3 Nos. |
Vehicular Underpasses | 12 Nos. |
New R.O.B | 1 Nos. |
New Major bridges | 4 Nos. |
Minor Bridge | 13 Nos. |
Grade Separator | 12 Nos. |
Total Culverts:. | 64 Nos. |
Truck Lay by | 2 Nos. |
Bus Shelters | 58 Nos. (both sides) |
Rest Areas | 2. Nos |